Project Progress Update 2019
This update is to give you an overview on what has already happened at the Kisarawe School Project and how we plan to continue. For more information on the project, please refer to the project menu.
What has happened
Before 2016
- land has been purchased
2016
- school/campus farm running (cashew nuts, mangoes & vegetables)
- soccer pitch ready
- school administration office and store built
- water well dug
- built office toilets and septic tank
- start of building first classroom till roofing level
- brick making machine & brick making in progress
2017
- school/campus farm running (cashew nuts, mangoes & vegetables)
- first classroom is roofed, floored and doors/windows are fitted
- 2 more classrooms built till roofing level
- security house and store built
- beefarming started
- chicken coop built and keeping chickens
- church and community centre built and in use
2018
- finished and furnished 1st block of 3 classrooms
- student toilets and septic tank built
- kindergarten first class has started
- build 2nd block of 3 classrooms
- furnished staff office
- build chicken-farm
- put up a playground for the school
2019 first half
- kindergarten first and second class running
What has been planned for
2019
- finish building and roofing classroom blocks 2 and 3
- start vocational training in sewing
- school kitchen
- library
- hostel
2020
- staff housing
- solar energy program