This update is to give you an overview on what has already happened at the Kisarawe School Project and how we plan to continue. For more information on the project, please refer to the project menu.

 

 

 

 

What has happened

Before 2016

  • land has been purchased

2016

  • school/campus farm running (cashew nuts, mangoes & vegetables)
  • soccer pitch ready
  • school administration office and store built
  • water well dug
  • built office toilets and septic tank
  • start of building first classroom till roofing level
  • brick making machine & brick making in progress

2017

  • school/campus farm running (cashew nuts, mangoes & vegetables)
  • first classroom is roofed, floored and doors/windows are fitted
  • 2 more classrooms built till roofing level
  • security house and store built
  • beefarming started
  • chicken coop built and keeping chickens
  • church and community centre built and in use

2018

  • finished and furnished 1st block of 3 classrooms
  • student toilets and septic tank built
  • kindergarten first class has started
  • build 2nd block of 3 classrooms
  • furnished staff office
  • build chicken-farm
  • put up a playground for the school

2019 first half

  • kindergarten first and second class running

 

What has been planned for

2019

  • finish building and roofing classroom blocks 2 and 3
  • start vocational training in sewing
  • school kitchen
  • library
  • hostel

2020

  • staff housing
  • solar energy program

 


We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.